Just one example: Plans for the Meta data center in Louisiana that David focused on in his story have expanded, and its power needs have too. The local utility went from three planned natural-gas plants to 10. And as I wrote in a new story this week, data center developers are now looking beyond the grid and planning to build their own off-grid gas power plants. How did we get here?
If you want to understand the future of the grid, one way to do it is by looking at interconnection queues—lists of power plants that have requested a connection to the system. In recent years these queues have been dominated by renewables like wind and solar power, which are generally the cheapest way to build new energy capacity today.
But there’s been a shift in some places, particularly for PJM, the country’s largest power grid operator, which covers parts of 13 states in an area stretching from Illinois to Washington, DC. PJM has seen a major uptick in natural-gas proposals. In August, the operator announced that it had accepted proposals for 715 total projects with a capacity of over 200 gigawatts to join its queue. Nearly half that total capacity represented natural-gas plants.
If all the projects in the queue were built, it would increase the fossil-fuel share on PJM’s grid from 61% to 67%, according to an analysis by Kevin Kircher, an energy modeler and assistant professor of mechanical engineering at Purdue.
PJM’s queue is reflective of a bigger trend across the US. Natural gas is already the single biggest source of electricity in the country, and it has basically become the default to meet exploding power demand.
This AI-driven rush is already affecting greenhouse-gas emissions for tech companies. Meta’s emissions are up 45% over last year’s, according to the company’s recently released 2026 Sustainability Report. That’s even higher than the jumps from fellow hyperscalers Google (18%), Amazon (16%), and Microsoft (25%). The company is also “reevaluating” its 2030 goal to reach net-zero emissions, according to the report, though there aren’t details about how or when it might reach a decision there.